1 yearInitial supply contract
9 a.m.–3 p.m.Fixed energy-unit-rate window
20 yearsOptional longer contract
1,539 sitesCumulative sites developed, Sept. 2026
Important: The advertised fixed rate applies to the energy unit charge from 9 a.m. to 3 p.m., not to an entire electricity bill. Midterm cancellation is generally restricted. Savings from this new campaign have not yet been demonstrated.

A twenty-year power decision becomes a one-year test

A 20-year electricity contract is a consequential commitment for a business. Factories alter production, retailers close or relocate premises, and the cost of energy changes with regulation and technology. Yet long contracts can give renewable developers the financial certainty they need. On November 16, 2026, Tokyo-based i GRID SOLUTIONS introduced an experiment in bridging those competing interests: its Circular Power One-Year Start Plan campaign offers a one-year entry into a service ordinarily contracted for 20 years.

The proposal is more nuanced than a cheap green-electricity trial. It allows companies to collect a year of real consumption and billing evidence before deciding whether to accept a much longer contract. The practical question is whether it transfers useful flexibility to the buyer without masking costs that remain outside the fixed-price promise.

The fine print: six daytime hours, not a fixed annual bill

The company says the energy unit rate matches its standard 20-year contract. For the 9 a.m. to 3 p.m. window, that rate is fixed for the first year without a fuel-cost adjustment. After the year, a buyer can end the arrangement or convert to a 20-year agreement, carrying over the unit rate. The release also says changes in law or the regulatory system may prompt a discussion about adjusting rates.

None of those statements establishes a flat monthly bill. The amount a customer pays still depends on electricity consumed, use outside the specified daytime window, fixed charges and other contract terms. There is no public universal price per kilowatt-hour, and the company has not supplied a side-by-side annual-bill simulation that would prove savings for an ordinary industrial customer.

One year does not mean cancel any time

The campaign is not a month-to-month subscription. Cancellation during the initial year is generally prohibited. The announcement identifies a no-penalty accommodation for facilities that close or relocate, but directs prospective customers to obtain the detailed terms. The precise conditions at the end of the year are also to be explained individually, and the campaign may end without advance notice.

For a finance or procurement committee, those details matter almost as much as the unit price. What happens if a tenant leaves a property, if electricity demand drops sharply, or if the customer decides to contract with another supplier after twelve months? Before signing, a business should obtain the formal offer, tariff schedules, allocation of network charges and written exit provisions.

A different way of using the roofs Japan already has

The underlying service, marketed in Japanese as Junkangata Denryoku (循環型電力), aggregates surplus renewable electricity from solar installations that i GRID operates across commercial roofs. A supermarket, logistics hub or factory may generate more electricity at midday than it can use on site. Instead of treating the excess as an isolated byproduct, the company organizes supply to other businesses through the power system.

The company classifies the arrangement as an off-site power purchase agreement, or PPA. This does not mean a private wire physically connects an individual roof to an individual customer. Grid delivery, electricity contracting and renewable attributes must be managed within Japan’s established electricity market. It is also not simply a certificate-only deal. The details of individual retail contracts and attribute allocation remain essential to assessing the environmental claim.

Three types of corporate PPA, and why definitions matter

In an on-site PPA, a developer typically owns or operates a solar installation at the buyer’s premises, and the electricity is consumed there. In a physical off-site PPA, generation occurs elsewhere and electricity is supplied via the grid, usually together with the associated renewable attributes. A virtual PPA, by contrast, generally involves a financial settlement and transfer of attributes without delivering that specific electricity through the buyer’s retail supply arrangement. These distinctions are laid out by Japan’s Ministry of the Environment and the Accounting Standards Board of Japan.

As described in its release, Circular Power belongs to the off-site supply category. Treating all green-power contracts as equivalent would obscure the very problem this product seeks to solve: pooling output from many distributed sources and aligning it with customers whose premises cannot necessarily support their own generating equipment.

How Japan moved from guaranteed tariffs to corporate buyers

Japan’s feed-in tariff, introduced in July 2012, accelerated solar deployment by providing eligible generators with predictable purchase conditions. The later growth of daytime solar production also exposed challenges involving grid capacity, variable generation and the value of electricity at different hours. In April 2022, Japan introduced the feed-in premium system for relevant projects, making market-facing operation more important.

Corporate PPAs are part of the next chapter. Buyers may want long-term renewable supply and a more predictable energy-cost component; generators want revenue arrangements that support investment. But 15- and 20-year arrangements can be challenging for smaller procurement teams and businesses with uncertain locations or demand. The Renewable Energy Institute’s March 2026 study reports that corporate PPAs have expanded beyond major corporations to medium-sized and smaller buyers. Shorter entry terms could lower a decision-making barrier, but their effect on actual project development remains unproven.

The supplier began as a cost-cutting consultancy

i GRID’s lineage reaches back to February 2004, when it was established in Osaka as Cost Reduction Research Institute. It introduced an energy-management service in 2005, entered solar-power development in 2011, began electricity supply in 2014 and adopted the i GRID SOLUTIONS name in 2015. From 2017 it developed the on-site PPA model at commercial buildings, then expanded toward integrating distributed power assets, energy trading and digital coordination.

In 2024 it absorbed two group companies as part of a broader operational reorganization. It listed on the Tokyo Stock Exchange Growth Market on July 29, 2026, with securities code 603A. This history explains why its latest initiative combines procurement design with a broad rooftop generation footprint: the firm has spent two decades evolving from advice about electricity bills into a developer and organizer of distributed supply.

A nationwide platform—but what do the project counts measure?

In August 2026, the company said it had reached on-site PPA development in all 47 Japanese prefectures, exceeding 1,500 project sites. The November release reports cumulative development of 1,539 solar facilities totaling approximately 402 megawatts as of the end of September. Those are company-reported development figures. They should not automatically be read as 402 MW producing power today, still less as 402 MW available exclusively for Circular Power customers.

The more revealing operating figures would include actual generation, the volume left unused by host buildings, volumes supplied under off-site contracts, and the matching of solar output with the customers’ consumption hours. Those granular figures were not established by the campaign announcement.

A real-world precedent in Toyohashi

In October 2026, i GRID announced that Volkswagen Group Japan had adopted Circular Power for its Toyohashi headquarters and import center, with supply beginning September 1. The companies describe an expected annual delivery of approximately 4.6 gigawatt-hours, a 100% renewable share at the covered site and an estimated annual reduction of 2,053 metric tons of carbon dioxide. The application is especially relevant because the operator cited building structure and roof constraints that made some on-site installations difficult.

Those figures are prospective or calculated company estimates, not a third-party audit of an entire operating year. Nor is the Toyohashi agreement evidence that anyone has yet completed the newly offered one-year trial. It shows how the underlying service can be applied, not how the campaign will perform for its future customers.

The economics of the six-hour solar window

Choosing 9 a.m. to 3 p.m. is hardly arbitrary: it overlaps with significant daytime solar production. Commercial facilities with reliable midday demand may have the clearest opportunity to evaluate the offer, although actual value depends on each customer’s load profile and the detailed rate. A continuously operating refrigerated warehouse or industrial plant may face quite different exposure in the remaining eighteen hours.

A meaningful comparison requires interval-meter data, an itemized existing bill, a modeled new contract and clearly identified renewable attributes. Buyers should also examine provisions for outages, changes in demand and the end-of-year decision. A fixed daytime energy charge is only one part of electricity-cost risk.

Is moving existing surplus the same as building new renewables?

Climate-accounting language matters. Helping another company use surplus from an existing rooftop system can improve the commercial use of distributed generation. It is not automatically the same as financing a new wind or solar plant that would otherwise never have been built—a question often described through additionality. Both can be valuable, but they should not be presented as identical outcomes.

To evaluate an individual customer’s emissions claims, readers would need the origin and vintage of renewable attributes, proof of ownership and retirement, safeguards against double counting, and the relevant accounting methodology. The release does not independently verify new generating capacity or quantified emissions savings attributable to this one-year offer.

The real product arrives in the customer’s year-end report

i GRID promises an experience-based report after the first year, intended to help the business decide whether a 20-year extension is justified. Such a report could be most useful if it separates cost, volume, time-of-use patterns, renewable attribution and contract risks. A promotional comparison alone would be less informative than figures that a buyer’s finance department can reconcile to meter readings and invoices.

The public materials do not establish a universal tariff, the complete terms for every customer, a minimum contract volume or the number of companies that will sign up. Those matters remain open, and purchasers should not substitute a press release for a signed tariff and supply agreement. The larger significance of the campaign is an attempt to make a long-term energy decision evidence-led. Whether that design materially increases renewable procurement will become clearer only after customers finish their first year.

Exchange-rate reference supplied for this edition: US$1 = ¥159.32 as of November 17, 2026, 03:53 UTC. No dollar equivalent is presented because no universal contract price or amount is disclosed.

Primary sources and limits of verification

Independent reporting and analysis based on materials available through November 16, 2026. No direct interviews were conducted. Complete tariffs, base charges, individual exit provisions, minimum volumes, attribute allocations, measured savings and campaign subscription figures were not verified.

  1. i GRID: 2026年11月16日「循環型電力」1年契約キャンペーン
  2. i GRID: 「循環型電力」キャンペーン案内
  3. i GRID: 沿革
  4. i GRID: 47都道府県でのオンサイトPPA開発
  5. i GRID: フォルクスワーゲン グループ ジャパン導入事例
  6. Ministry of the Environment: オフサイトコーポレートPPAの形態
  7. ASBJ: コーポレートPPAの整理
  8. Renewable Energy Institute: コーポレートPPA 日本の最新動向2026
  9. Agency for Natural Resources and Energy: FIT・FIP制度の経緯
  10. i GRID: IR FAQ(上場日)